RMP - PMI EXAM

Risk Planning

Risk Planning

 

Usually, risk plan is the first effort that is being done through project risk management.
However, in some projects, the top management in the organization identifies high level risks in the project charter and these high level risks are the input for the project manager that clarify an image of what risks are significant and  important for the top management.

Risk plan is a subsidiary plan of project management plan that describes how risk management activities will be managed throughout the project phases. This plan performs as a guide of how you will accomplish all the activities of risk management. It defines the tools and approaches that will be used, roles and responsibilities, estimated budget for these activities, risk categories, risk definitions, reporting formats, and auditing procedures.


Through the next paragraphs, we will show examples for some of these components of risk management plan.


1 – Tools & Approaches


Risk management activities may be done manually or using computer software programs. These software programs expedite, facilitate, and fully control the of risk management activities. These programs can be integrated with other organization systems such as scheduling, costing, and ERP systems. The capabilities of these programs are not only for calculation and assessment; however it can track and communicate responsibilities to the team assigned for these tasks and also for the management to be able to follow the status and take actions.


2 –  Roles and Responsibilities


Table-1 shows an example for the roles and responsibilities.

Team member
Name
Role Responsibilities
Ahmed Arafa Risk
Manager
1. Develop the risk management plan
2. Manage the risk management team.
3. Follow up that risk management activities are being done
with the valid manner in the right time.
4. Monitor contingency reserve and maintain the sufficiency
of monetary in reserve fund.
5. Report on risk management activities.
Ayman Nagy Risk
Software
Admin
1. Administrate the risk management program.
2. Maintain and monitor the privilege of users.
Wael Samy Risk
Engineer
1. Share in the identification of risks.
2. Develop the qualitative and quantitative analysis.

Table-1 : Roles and Responsibilities


3 –  Timing and Frequency


Risk management activities are being done according to a time scheduling that is being developed by the risk manager and in conformity of project management vision.


Figure-1 is an example of risk management activities time scheduling.

Figure-1 : Risk Activities Time Schedule


Risk management meetings could be determined to be as a separate meeting and held on weekly, bi-weekly, or monthly basis. The common practice is that risk management activities are being discussed in the progress status weekly meeting.

 

4 –  Risk Categories


Risk Categories can be illustrated in a list or a risk breakdown structure. Figure-2 is an example of risk breakdown structure.

 

Figure-2 : Risk Breakdown Structure

 

5- Risk Definition


This is the classification criteria that will be used further in order to qualitatively assess risks. Table-2 shows an example of these limits.

Table-2 : Risk Classification Limits

 

6 –  Risk tracking and Reports format


This defines how risks will be tracked during project phases; and the formats of risk reports that will be used to communicate risk information through vertical and horizontal communication channels.

The Engineering Community

Recent Posts

How Artificial intelligence (AI) can optimize bridges design?

How Artificial intelligence (AI) can optimize bridges design? Introduction:   Bridges are important pieces of infrastructure that connect communities and…

7 months ago

How AI can help in Highways and Railways design?

How AI can help in Highways and Railways design?   Introduction:   Artificial Intelligence (AI) has emerged as a transformative…

7 months ago

Enhancing Road Modeling Efficiency : Leveraging ChatGPT with Civil3D

Enhancing Road Modeling Efficiency : Leveraging ChatGPT with Civil3D Introduction: Road modeling is a critical component of civil engineering and…

11 months ago

What are Stirrups and Why we Use Them?

What are Stirrups and Why we Use Them?   Steel reinforcement is an essential component of reinforced concrete, providing tensile…

1 year ago

Why Are Spiral Curves Important? Benefits And Elements Of Spiral Curve

Why Are Spiral Curves Important? Benefits And Elements Of Spiral Curve   1. Introduction:   Spiral curves are an important…

1 year ago

The Main Types Of Tunnels

The Main Types Of Tunnels   Tunnels have been used for various purposes throughout history, from transportation and infrastructure to…

1 year ago

This website uses cookies.