Earned Value Management Excel Template

Earned Value Management Excel Template

 

Overview:

EVM integrates project scope, time & costs through periodic measurements of actual cost & work completion.

It views project progress in terms of cost as a function of time against a firm baseline set up at the project start. When the project is originally planned, it is divided into Work Breakdown Structure (WBS) & further sub-divided into work packages.

These work packages are assessed for cost estimates & scheduled in a time sequence. Taken together, WBS, master schedule & cost budgets form the baseline, represented as a graph of planned costs over time. This is the planned value (PV).

It tells how the costs will flow over time as planned. During the project execution, actual costs (AC) & the quantum of work completed are periodically noted.

 

Earned value Management Formulas

Completion of work is pro-rated to equivalent monetary value based on the budgetary costs for the work packages completed (work-in-progress packages are assessed on % completion).

This is the earned value (EV). These three numbers, i.e. PV, AC, and EV drive the operation of Earned Value Management. In detail, (EV – AC) measures cost performance and (EV – PV) measures schedule performance. When measuring at periodic intervals, EVM focuses on the flow rates of actual cost and completion against the planned cost and completion.

PV, EV, and AC make it possible to compute cost & time variances, as well as extrapolate how much cost & time would be required for project completion.

Simple calculations based on these numbers yield several ratios for project control. Of these, three ratios can be regarded as important: Cost Performance Index (CPI), Schedule Performance Index (SPI)  & Cost Estimate at Completion (CEAC).

By giving historical & forward information about the project, EVM becomes a tool for monitoring & course corrections.

Earned Value Management Excel Template

-This Earned Value Management Excel Template will help you in your project

-This Earned Value Management Excel Template is helpful for creating CPI & SPI

 

Download Link

Source: bibloteka.com

To download More Project Management Templates, visit www.managementproject.net

The Engineering Community

Recent Posts

How Artificial intelligence (AI) can optimize bridges design?

How Artificial intelligence (AI) can optimize bridges design? Introduction:   Bridges are important pieces of infrastructure that connect communities and…

7 months ago

How AI can help in Highways and Railways design?

How AI can help in Highways and Railways design?   Introduction:   Artificial Intelligence (AI) has emerged as a transformative…

7 months ago

Enhancing Road Modeling Efficiency : Leveraging ChatGPT with Civil3D

Enhancing Road Modeling Efficiency : Leveraging ChatGPT with Civil3D Introduction: Road modeling is a critical component of civil engineering and…

11 months ago

What are Stirrups and Why we Use Them?

What are Stirrups and Why we Use Them?   Steel reinforcement is an essential component of reinforced concrete, providing tensile…

1 year ago

Why Are Spiral Curves Important? Benefits And Elements Of Spiral Curve

Why Are Spiral Curves Important? Benefits And Elements Of Spiral Curve   1. Introduction:   Spiral curves are an important…

1 year ago

The Main Types Of Tunnels

The Main Types Of Tunnels   Tunnels have been used for various purposes throughout history, from transportation and infrastructure to…

1 year ago

This website uses cookies.