Question #1
Your developer has provided u with an estimate based on the “cost per line of code”.
What type of estimate did the developer use to provide this information?
A. Parametric estimating.
B. Bottom-up- estimating.
C. Analogues estimating.
D. PERT estimating.

Question #2
A definitive estimate is:
A. Top-down estimating.
B. Created during initiation.
C. Within a range of -10% to +25% of actual.
D. The most expensive to create.

Question #3
All of the following are inputs to the cross-budgeting process expect?
A. cost estimate.
B. project schedule.
C. risk management plan.
Deactivate duration estimates.

Question #4
Analogues estimating is a tool technique used in both Time and Cost management
process. What is the best description of how analogues estimating is performed?
A. by-bottom-up estimating techniques.
B. obtaining management options of the estimate of each task.
C. by-top-down estimating techniques.
D. based on historical costs.

Question #5
Cost budgeting is defined as
A. the estimated total cost of the Project when done.
B. allocating the cost estimates to the individual work items.
C. developing estimates of the cost of the resources needed to complete project activities.
D. the sum of the approved cost estimates.

Question #6
Due to recent company downsizing, u can only authorize 1 of the 2 projects u really
planned to complete this year. You have decided to select the project with the NPV of $95k
and proceed to cancel the other project which had an NPV of $37k what are the
opportunity costs associated with this new decision?
A. $37k
B. $95k
C. $123k
D. $58k

Question #7
Analogues estimating is a form of
A. earned value.
B. expert judgment.
C. cost planning
D. parametric modeling.
The Engineering Community

Recent Posts

How Artificial intelligence (AI) can optimize bridges design?

How Artificial intelligence (AI) can optimize bridges design? Introduction:   Bridges are important pieces of infrastructure that connect communities and…

7 months ago

How AI can help in Highways and Railways design?

How AI can help in Highways and Railways design?   Introduction:   Artificial Intelligence (AI) has emerged as a transformative…

7 months ago

Enhancing Road Modeling Efficiency : Leveraging ChatGPT with Civil3D

Enhancing Road Modeling Efficiency : Leveraging ChatGPT with Civil3D Introduction: Road modeling is a critical component of civil engineering and…

11 months ago

What are Stirrups and Why we Use Them?

What are Stirrups and Why we Use Them?   Steel reinforcement is an essential component of reinforced concrete, providing tensile…

1 year ago

Why Are Spiral Curves Important? Benefits And Elements Of Spiral Curve

Why Are Spiral Curves Important? Benefits And Elements Of Spiral Curve   1. Introduction:   Spiral curves are an important…

1 year ago

The Main Types Of Tunnels

The Main Types Of Tunnels   Tunnels have been used for various purposes throughout history, from transportation and infrastructure to…

1 year ago

This website uses cookies.